|

The
S-Shape Curve
Which do you practice: the
"50/70 Rule" or the unreliable "50/50 Rule"?
by Neal Whitten,
PMP, Contributing Editor
HAVE YOU EVER
NOTICED that the "linear 50/50 rule" doesnt seem
to work well on your projects? That is, if you have an activity such
as Prepare the Products Documentation, Code the Products
Modules, or Run the System Test Scripts, when half of the allotted time
for the activity has elapsed, you are 50 percent completed with the
activity. Yet, when the remaining 50 percent of the time expires, the
activity has not completed? This is a common problem on projects with
activities that are made up of multiple so-called equivalent-weighted
tasks.
For
example, if we have 100 pages of material to write in 20 days (Prepare
the Products Documentation), we expect the progress of writing
the pages to represent a linear progression. That is, each page takes
the same amount of time to write and that five pages can be expected
to be completed every day. But the reality is that if you are only 50
percent complete with an activity when half the time has elapsed, the
activity is almost certain to be completed late.
So,
what can we do different? When planning an activity made up of many
tasks that are approximately of the same level-of-effort, do not use
the linear 50/50 rule. Instead, use the "S-shape curve 50/70 rule."
That is, when 50 percent of the time has elapsed, 70 percent of the
work must have been completed. The remaining 30 percent of the work
must be completed in the remaining 50 percent of time.
Lets
look at the exhibit to better understand what happens. The S-shape curve
is common for planning many types of endeavors. It suggests that progress
usually is slow at the start of an activity, builds to a peak when productivity
is at its very best, and then slows again during the more difficult
phase of completing the activity. Almost every activity you take on
in life tends to play out this way. This is why many of us say we are
on schedule midway into an activity, and believe we are, yet often are
late in completing the activity.
THE NEXT TIME
you are creating a plan for yourself, or are working with your team
or project members in creating a plan, make sure that your plan takes
into account the realities of the S-shape curve. Furthermore, when your
progress is being tracked, show the planned progress as an S-shape curve
where the vertical axis depicts the quantity being measured, such as
the number of pages to be written, modules to be coded, or test scripts
to be run. Then report your actual progress against your plan that is
depicted as an S-shape curve.
Neal Whitten, PMP, president of
The Neal Whitten Group (www.nealwhittengroup.com), is a speaker, trainer, consultant,
mentor, and author in project management and employee development. His books include
The EnterPrize Organization: Organizing Software
Projects for Accountability and Success and Managing
Software Development Projects: Formula for Success.
|
This material
is reprinted from PM Network magazine (October 1999) with permission
of the Project Management Institute Headquarters, Four Campus
Boulevard, Newtown Square, PA 19073-2399 USA. Phone: (610) 356-4600.
Fax: (610) 356-4647. Project Management Institute (PMI) is the
worlds leading project management association with over
50,000 members worldwide. For further information, contact PMI
Headquarters at (610) 356-4600 or visit the web site at www.pmi.org.
"PMI" and "PM Network" are trademarks of the
Project Management Institute, Inc.
©
2000 Project Management Institute, Inc. All rights reserved.
|
ARTICLES
| HOME
| TOP
|