|

The
Planning of Project Documents
Parse document-related activities
into a series of smaller activities.
by Neal Whitten,
PMP, Contributing Editor
I FREQUENTLY
REVIEW project plans. A common weakness I encounter is the underplanning
of project documents. Project documents include any documents that must
be prepared and approved during a project; examples are requirements,
specifications, contracts with vendors, design documents, test plans,
and publications that will be delivered to the client along with the
final product.
For
example, if a project plan identifies an activity as "Test Plan"
and shows a duration of six weeks, what does this mean? Does it mean
that the Test Plan document can be prepared, reviewed, updated, and
approved all in six weeks? Or does it mean only that the Test Plan will
be prepared? Big difference!
Document-related
activities should be parsed into smaller, more discrete activities when
developing a project plan. These discrete activities are referred to
as document implementation phases. The logical sequence of these
phases is preparation, review, update, approval, and refresh.
Lets briefly look at each of these five phases.
Preparation.
This is usually the longest of the phases and can vary from several
hours for very small, simple documents to many weeks for large, complex
documents.
Review.
This phase begins when the document is distributed for examination.
This phase is typically several days to several weeks in duration, depending
on the document type, size, and availability and proximity of reviewers.
Documents distributed for review should be essentially completeno
sections should be missing or significantly deficient. The goal is for
all information to be available, complete, and accurate.
Update.
This phase is used to modify a document in response to comments from
reviewers. Time is set aside to react to comments and concerns that,
once addressed, will ensure a better product or project. This phase
may be from several days to several weeks in duration depending on the
document and the quantity and complexity of the problems identified.
All updates to the document should be highlighted, such as the use of
revision bars in the margins. This will allow reviewers to locate quickly
the most recent changes to the document.
Approval.
This is the final opportunity for responses on a document. This phase
is called approval because final agreement on the documents contents
must be reached here. This phase might take from several days to several
weeks.
Refresh.
The last phase is used to record any changes to the document that have
occurred during the approval phase. The document is then distributed
for information purposes only; no more comments are expected or solicited.
This phase could take as little as one hour or as long as several weeks.
Some
documents might need only the three phases: preparation, approval, and
refresh. These documents are typically small in size, cause little controversy,
and would require little change from a first review. Documents that
require all five phases are those that are considered critical or complex
project documents. To omit the review and update phases for documents
that are considered primary is usually a grave mistake.
Although
the five phases described here are adequate for most documents, you
might choose to identify other phases for some documents. For example,
separate phases related to customer validation or inspection might be
added.
However
many phases you assign to a document, it is important to separately
identify, plan, and track these phases. Returning to our original example,
"Test Plan6 weeks" is better planned and tracked by
parsing that document into smaller activities, such as Prepare Test
Plan2.5 weeks, Review Test Plan1 week, Update Test Plan1
week, Approve Test Plan1 week, and Refresh Test Plan.5 weeks.
PROJECT PLANNING
IS all about getting in control. Dividing a document-related
activity into smaller activities helps you do just that.
Neal Whitten, PMP, president of
The Neal Whitten Group (www.nealwhittengroup.com), is a speaker, trainer, consultant,
mentor, and author in project management and employee development. His books include
The EnterPrize Organization: Organizing Software
Projects for Accountability and Success and Managing
Software Development Projects: Formula for Success.
|
This material
is reprinted from PM Network magazine (December 2000) with permission
of the Project Management Institute Headquarters, Four Campus
Boulevard, Newtown Square, PA 19073-2399 USA. Phone: (610) 356-4600.
Fax: (610) 356-4647. Project Management Institute (PMI) is the
world's leading project management association with over 50,000
members worldwide. For further information, contact PMI Headquarters
at (610) 356-4600 or visit the web site at www.pmi.org.
"PMI" and "PM Network" are trademarks of the
Project Management Institute, Inc.
©
2000 Project Management Institute, Inc. All rights reserved.
|
ARTICLES
| HOME
| TOP
|