|

Project
Planning: Frequently Asked Questions - Part 1
"The beginning is the
most important part of the work," said Plato. I agree!
by Neal Whitten,
PMP, Contributing Editor
Effective project planning is
vitally important to the success of a project, yet on many projects
planning is weak. Here are responses to some frequently asked questions
about this crucial activity.
Q.
What is the primary purpose for a project plan? Project planning
is about getting in control. Until a project has a comprehensive
plan to follow, it cannot convincingly be defended as being under control.
The project plan serves as a road map of project activities, is critical
to achieving a healthy productivity rate for the project's members,
is the keystone for project communications, and is the baseline from
which to gauge progress. Note: Project tracking is about staying
in control and can only be effective after a reasonable plan is
in place from which to track.
Q.
When should a project plan be started? A preliminary project plan
should be available within the first week that a project manager
(PM) is assigned to a project. It should address the next two to four
weeks of activities and requires no approval other than by the PM. It
is used to ensure that the PM, as well as project members coming onboard,
are making reasonable progress. Until a comprehensive project plan can
be put in place, the PM must always have a near-term plan from which
to pace progress.
Q.
What events should occur before a comprehensive project plan can be
created? Minimally, these events should occur: the project manager
is assigned; the requirements (problems to be solved) are completed
and approved; a scope statement (very-high-level solution addressing
the problems) is completed and approved; and a critical mass of project
members are assigned and working the project. For some projects, detailed
specifications or a statement of work also is completed and approved.
For the more process-mature projects, additional exhibits are in place,
such as a project management methodology and a project charter defining,
among other things, roles and responsibilities.
Q.
It appears that the PM is responsible for the project plan. True?
True. The project plan is created according to the direction given by
the project manager. Every project member contributes to it, and the
PM ensures that all aspects of the plan are carefully reviewed and approved.
The PM defends the right plan on behalf of all project stakeholders
and is held personally accountable for both the completeness and the
performance of the plan.
Q.
Is it wrong for the client, sponsor, or head executive to preset the
project completion date? Not at all! This date is helpful to allow
the project team to understand the sense of urgency of the project and
to attempt to achieve the target date. A problem arises only if the
project team cannot possibly achieve the target date, yet it is mandated
anyway.
Q.
Referring to the last question/answer, what can the PM do if directed
by a superior to provide a plan that, on paper, appears to achieve the
end date but in reality is unrealistic? The project manager has
the responsibility to defend the right plan. If the PM is unsuccessful,
then several steps can be taken. (1) Solicit a respected third party
to assess the reasonableness of the project plan with the expectation
that that person backs up the PM's assessment. (2) Put metrics in place
so that early warning signs can be seen if the progress of the project
plan begins to wane. (3) At the end of each major phase of the project
plan, add the activity, "Resize Project Plan." This will allow
a more accurate estimate for the remaining phases.
Q.
But what if the project end date is contractual? Isn't it a waste of
time to resize the project? All the more reason to resize the project
when better estimates can be provided. If you have a committed project
completion date, it is imperative to understand the obstacles so that
they can be mitigated. Perhaps the original end date cannot be achieved;
however, everyone will be pulling together to minimize the damage.
NEXT MONTH,
IN PART 2, I'll respond to more frequently
asked questions about project planning, while continuing on a quest
to add more thoughtfulness to an often ineffectively performed activity.
Neal Whitten, PMP, president of
The Neal Whitten Group (www.nealwhittengroup.com), is a speaker, trainer, consultant,
mentor, and author in project management and employee development. His books include
The EnterPrize Organization: Organizing Software
Projects for Accountability and Success and Managing
Software Development Projects: Formula for Success.
|
This material
is reprinted from PM Network magazine (September 2000) with permission
of the Project Management Institute Headquarters, Four Campus
Boulevard, Newtown Square, PA 19073-2399 USA. Phone: (610) 356-4600.
Fax: (610) 356-4647. Project Management Institute (PMI) is the
world's leading project management association with over 50,000
members worldwide. For further information, contact PMI Headquarters
at (610) 356-4600 or visit the web site at www.pmi.org.
"PMI" and "PM Network" are trademarks of the
Project Management Institute, Inc.
©
2000 Project Management Institute, Inc. All rights reserved.
|
ARTICLES
| HOME
| TOP
|