Earned Value - Quick Reference
Earned Value can be applied to answer key questions about your project.

What is the baseline cost of the project?
  BAC = Budget at Completion: The planned cost for the entire project.
Where should the project be today?
  PV = Planned Value: The planned cost for the planned work during a given period.
How much have we completed as of today?
  EV = Earned Value: The budgeted amount for the work actually completed.
How much has it cost as of today?
  AC = Actual Cost: The total cost incurred to accomplish the work during the period.
What is the difference between where the project was planned to be and where we are?
  SV = Schedule Variance = EV - PV
What is the percentage of work completed compared to the work that was planned (the schedule efficiency)?
  SPI = Schedule Performance Index = EV / PV
What is the difference between the value of what we actually accomplished and what was actually spent?
  CV = Cost Variance = EV - AC
What is the cost of the work completed compared to what was actually spent (the cost efficiency)?
  CPI = Cost Performance Index = EV / AC
What is the range of projected costs of the project when complete?
 

Range of costs

=
=
Min to Max
(BAC / CPI) to (BAC / (CPI x SPI))
What is the range of projected schedule durations of the project when complete?
 
Range of schedule durations
=
=
Min to Max
(PV duration / SPI) to (PV duration / (CPI x SPI))

“Ideas to help you become more successful”
© 2001 Neal Whitten; not-for-sale copies are permitted

BACK | HOME | TOP